Below is information on current and future road construction within the City.
Project
Start Date
Completion Date
Alternate Routes
11800 So Riverton Improvement Projects, Phase 3
Three part project to include: the addition of curb/gutter/sidewalk across the frontages of developed properties; sidewalk, property, and storm drain tie-in’s, and intersection improvements at 3600 West and 11800 South.
See Purchasing Web Page for Tabulation Awards
Lane Reduction’s Expected
July 2010
Sept, 2010
RDA Beautification Project Redwood Road
Roadway Completed; Landscaping to be completed in July 2010
Project includes the addition of curb/gutter/sidewalk across the frontages of properties; storm drain tie-in’s; asphalt and property tie-ins; Extensive landscape beatification.
See Purchasing Web Page for Tabulation Awards
April, 2010
August, 2010
2700 West &
1300 West
Street Light Retrofit
Project Complete
May 2010
July 2010
Public Works Wash Bay
Project Complete
May 2010
June 2010
11800 (2240 West -Redwood) Roadway Improvement Project
Project Complete
March, 2010
July, 2010
Overlay (4 Streets)
Doreen, Chartwell, 1830 West, Brindie Way
Project Complete
June 2010
June 2010
Micro Surface (6 Areas)
Project Complete
May 2010
June 2010
Slurry Seal (6 Areas)
Project Complete
May 2010
June 2010
ADA Ramps- Doreen Drive & 1830 West
Project Complete
April 2010
May 2010
ADA Ramps- Chartwell Area & Brindy Way
Project Complete
April, 2010
May, 2010
2010 Crack Seal Project (Micro-surface, Slurry Seal, and Overlay Area’s)